Inverse Definite Overcurrent Relay Response at Pencawang Masuk Utama Pagoh, Johor

Authors

DOI:

https://doi.org/10.54554/ijeeas.2024.7.02.001

Abstract

This paper focuses on modelling 132/11kV Pencawang Masuk Utama (PMU) Pagoh, Johor for assessing the Inverse Definite Minimum Time (IDMT) overcurrent relay in terms of relay response time using PSCAD software and comparing them with the calculated value. The relay is subjected to various fault conditions such as three phase fault, double phase and single-phase faults at different points of the network to observe the operating time. To ensure the reliability of the overcurrent relay, the response time was analysed. The response time were then being verified accordingly and the simulation result shows that the relay response time closely match the calculated value.

Downloads

Download data is not yet available.

Downloads

Published

2025-03-19

How to Cite

Hairi, M. H., Mohd Isira, A. ., Kamarudin, M., Packeer Mohamed, M., & Sobri, A. (2025). Inverse Definite Overcurrent Relay Response at Pencawang Masuk Utama Pagoh, Johor. International Journal of Electrical Engineering and Applied Sciences (IJEEAS), 7(2). https://doi.org/10.54554/ijeeas.2024.7.02.001